The impact of claims activity on insurance – 0221-01

Figure 8: Key underwriting criteria

● Natural Catastrophe exposures ● Geotechnical Conditions ● Site accessibility ● Bushfire & vegetation management

Project Location

● Proven / prototypical technology ● Product / Type Certification

● Wind rating & design ● Lightning protection ● Reliable supply chain ● Robust Warranties

Technology

● EPC and O&M Contractor experience / track record in sector ● OEM support / involvement in the project & appropriate warranties ● Proven quality assurance & control system ● Distance to connection points ● Bottleneck exposures ● Acceptable equipment redundancy & configuration ● Overhead / buried transmission lines ● Number of other projects using non-owned substation ● Established risk management procedures ● Float / time contingency in project schedule ● Standard Liquidated Damages regime ● Critical spares holding ● O&M agreement in place with asset management strategies and maintenance plans

Experience

Grid Connection

Risk Management